Terminal: Port Botany Expansion Project (PBE)
Date: 21 October 2009
Issue: Construction works notification to industry
Short Description of the Issue:
Please be advised of the upcoming construction works and changes to road conditions as part of the PBE project.
26 Oct - 23 Dec 2009 0700-1700hrs
Roads Affected: Foreshore Rd - between Penrhyn Rd and 2.5km west of Penrhyn Rd (East and West bound)
Road Closures: None
Traffic Conditions: None
26 Oct - 23 Dec 2009 1000-1500hrs
Roads Affected: Penrhyn Rd - b/w Foreshore Rd and 90m south of the intersection (Nth bound)
Road Closures: 1 of 3 Lanes
Traffic Conditions: None
26 Oct - 23 Dec 2009 2000-0500hrs
Roads Affected: Foreshore Road - b/w Penrhyn Rd and 3.2km West of Penrhyn Rd (East and West bound)
Road Closures: 1 of 2 Lanes
Traffic Conditions: Speed limit reduced variably 40km/h-60km/h during construction times only
23 Oct - 21 Nov 2009 & 23 Nov - 23 Dec 2009 1000-1500hrs
Roads Affected: Foreshore Rd - b/w Penrhyn Rd 3.2km west of Penrhyn Road (East and West bound)
Road Closures: 1 of 2 Lanes
Traffic Conditions: Speed limit reduced to 60km/h during construction times only
Impact of the Issue:
Sydney Ports would like to advise industry to be aware of the changed road conditions in the port precinct to assist in the construction works for the Port Botany Container Terminal Expansion Project.
Duration of Expected Delays: n/a
Commencement time of the issue: 23 October 2009
Approximate time to resolve the issue: n/a
Resolution action: Sydney Ports will monitor the situation with the construction works over the next 10 weeks. Please contact Trade and Logistics for further information if required 9296 4999.
Peter Zangari Media Relations Manager
Sydney Ports Corporation Level 4, 20 Windmill Street | Walsh Bay NSW 2000 Australia PO Box 25, Millers Point | NSW 2000 Australia
E: PZangari@sydneyports.com.au T: +61 2 9296 4995 | F: +61 2 9296 4731 | M: 0408 441 010 www.sydneyports.com.au
|